Foundation design to Eurocode 7 means showing that the ground can carry the loads without failing (ultimate limit states) and without moving too much (serviceability), using the partial factor method and the UK National Annex. In practice you build a ground model from the investigation, choose characteristic values, check bearing resistance, sliding and settlement for pads, strips and rafts or resistance and settlement for piles, then record it all in a geotechnical design report. This guide walks through that sequence and flags what is changing as the second-generation code arrives.
TL;DR
- Eurocode 7 (EN 1997) covers the geotechnical aspects of buildings and civil engineering works and works alongside EN 1990 for safety and serviceability.
- The current UK practice rests on BS EN 1997-1:2004 and its National Annex. The second generation splits the code into three parts, and BSI will withdraw first-generation UK adoptions on 30 March 2028.
- Spread foundation design checks every relevant limit state, then settlement. Pile design adds ground resistance and serviceability checks.
- A design report must record assumptions, data, methods and results, plus a supervision and monitoring plan.
- Overflow design, calculations and drawings can be handled by embedded remote engineers, so your team keeps the client relationship.
Table of Contents
- What Eurocode 7 covers
- The design logic: from ground model to verification
- Designing a pad, strip or raft foundation
- Pile design to Eurocode 7 in the UK
- The foundation design report
- What the second generation changes
- Common pitfalls in a foundation calculation package
- Getting extra capacity on foundation work
- FAQ
- Sources
What Eurocode 7 covers
Eurocode 7 applies to the geotechnical aspects of the design of buildings and other civil engineering works, and it is used together with EN 1990, which sets the principles for safety and serviceability (European Commission Eurocodes portal). The first generation has two parts: EN 1997-1:2004 (General rules) and EN 1997-2:2007 (Ground investigation and testing), both listed on the same portal.
For most UK foundation work you will still be working to BS EN 1997-1:2004 with its UK National Annex. The National Annex sets the nationally determined parameters, including which design approach and partial factors apply. If you want a broader view of how UK engineers apply the code day to day, our piece on how UK engineers apply EC7 in practice covers the wider picture.
The Institution of Structural Engineers publishes a manual for the geotechnical design of structures to Eurocode 7. It supports design to Parts 1 and 2, covering ground investigation reports, geotechnical design reports, overall stability, conventional foundations (pads, strips and piles) and characteristic values using the UK nationally determined parameters.
Eurocode 7 is also not only about the footing itself. A scheme with a basement brings groundwater, retaining walls and the foundation together, and a builder’s overview of basement foundation construction shows how those elements relate to the structure above. That is why the structural and geotechnical checks need to be read as one package.
The design logic: from ground model to verification
Ground model first
The ground model is a site-specific outline of the ground and groundwater, built from the investigation and other available data. The Ground Investigation Report is the factual source behind it (JRC guidance on assembling the ground model). The same guidance stresses that the ground model is the most likely picture given the data at that project phase, and that its uncertainties can be quantified and reduced as more data arrives.

In practice that means you should not treat an early desk study ground model as final. State what it rests on and what would change it.
Characteristic values
The JRC document on representative values recommends using statistics to obtain the characteristic value and engineering judgement to select a nominal value, then comparing the two critically. If they are similar, confidence rises. If they differ widely, examine why before going further (JRC representative values). Record that comparison in your calculation package. A reviewer will look for it.
Verification routes
EN 1997-1 allows design verification by the partial factor method or other reliability-based methods, prescriptive rules, testing, or the Observational Method (BS EN 1997-1:2024 introduction). For ultimate limit states using partial factors, the core inequality is Ed ≤ Rd. Rd comes from either the Material Factor Approach, which factors the soil properties, or the Resistance Factor Approach, which factors the resistances (see the JRC document above).
Which factors you apply, and whether you factor inputs or outputs, is a recurring source of confusion. We set it out in UK Eurocode 7 partial factors.
Designing a pad, strip or raft foundation
Section 6 of BS EN 1997-1:2004 covers spread foundations. It lists the limit states to consider: loss of overall stability, bearing resistance failure, punching failure, squeezing, sliding, combined failure in the ground and the structure, structural failure due to foundation movement, excessive settlement, excessive heave and unacceptable vibrations (BS EN 1997-1:2004, Section 6).
Not all of these govern every job. A sensible workflow:
- Define actions. Separate permanent and variable loads from the structural model, with eccentricities and horizontal components.
- Fix the geometry. Start with width, length and embedment depth, allowing for frost, shrink-swell and services.
- Check bearing resistance. The check requires Vd ≤ Rd for all ultimate limit states, with Rd determined under clause 2.4 of the same document.
- Check sliding and eccentricity. Horizontal loads and moments often govern narrow or heavily loaded pads.
- Check settlement. Include immediate, consolidation and creep components. The compressible layer is taken down to where the vertical stress from the foundation falls to 20% of the effective overburden stress, which is often around one to two times the foundation width (same source).
- Check the structural design of the footing. This is where geotechnical output meets Eurocode 2 reinforcement design.
A worked example to learn from
The ETC10 design examples cover pad foundations on dense sand and boulder clay, pile foundations in stiff clay and sand, earth and pore-water pressures on a basement wall, and an embankment on soft peat (ETC10 design examples). They are a good benchmark for checking your own spreadsheet against.
In the continuous footing in clay example (cu = 30 kPa) in the BS EN 1997-1 material, Design Approach 1 gives over-design factors of 2.03 for Combination 1 and 2.02 for Combination 2. Use figures like these to sanity-check a calculation rather than as a design target.
Our shallow foundation bearing guide goes deeper on capacity, checks and UK practice.
Pile design to Eurocode 7 in the UK
Pile design uses the same philosophy but adds resistance from shaft and base, and checks on settlement and group behaviour. A useful worked case comes from a software tutorial: a 10 m long, 400 mm square concrete pile in 8 m of medium-strength sandy clay (cu = 45 kPa) over medium-dense gravelly sand (phi’ = 36 degrees), carrying 650 kN permanent and 250 kN variable vertical load. The tutorial determines the minimum pile length under the UK and Irish National Annexes (Geocentrix RePUTE tutorial).
Whatever method you use, the logic of a pile check is the same:
- Build the ground profile with characteristic strengths by layer.
- Establish the design load from factored permanent and variable actions.
- Compute the design resistance and show that it exceeds the design load with the factors required by the UK National Annex.
- Check settlement and, where relevant, negative skin friction or lateral loading.
- Confirm the approach to testing, since pile load tests can be used to verify or refine the design.
Once the piles are sized, the structural work moves to the cap and ties. Our pile cap design guide covers two to four pile caps, and for walls retaining ground, matching walls to ground sets out the equivalent approach.
The foundation design report
The Geotechnical Design Report records the assumptions, data, methods of calculation and results of the verification of safety and serviceability. Section 2.8 of BS EN 1997-1:2004 says it should normally include:
- a description of the site and surroundings;
- the ground conditions;
- the proposed construction, including actions;
- design values of soil and rock properties, with justification;
- the codes and standards applied;
- statements on site suitability;
- geotechnical calculations and drawings;
- foundation design recommendations;
- a note of items to be checked during construction.
The report must also include a plan of supervision and monitoring, and an extract covering supervision, monitoring and maintenance must go to the owner or client (BS EN 1997-1:2004).
During detailed design the ground model develops into the Geotechnical Design Model. During execution, both are used to check the ground actually encountered and to back-analyse monitored behaviour (ISSMGE paper on the second generation). A report that makes the link between the two explicit makes site queries much quicker to resolve.
We cover layout and issue in what to include in a foundation design report and how to issue it.
What the second generation changes
The second-generation Eurocode 7 is split into three parts: EN 1997-1 (General rules), EN 1997-2 (Ground properties) and EN 1997-3 (Geotechnical structures). BS EN 1997-1:2024 is the UK implementation of the first of these, and BSI will withdraw UK adoptions of first-generation Eurocodes on 30 March 2028 (BS EN 1997-1:2024 preview). BS EN 1997-2:2024 (Ground properties) carries a National Annex with the UK national choices (NBS publication index).
A summary lecture by Dr Andrew Bond lists the headline technical changes: no more Design Approaches, a simpler choice of partial factors, a Material Factor or Resistance Factor Approach, better treatment of groundwater pressures, consequence separated from hazard, and Geotechnical Categories that drive real decisions (Geocentrix lecture on the second generation).
For spread foundations, the ISSMGE paper notes that partial resistance factors sit in Part 3, Subclause 5.6, Table 5.2, with partial material factors in Part 1, Table 4.8. It also notes a clearer distinction between settlement and tilting caused by load eccentricity, and that National Annexes will specify the factoring approach (ISSMGE on second-generation spread foundations).

What to do now: keep live projects on the code your contract names, but structure new calculation templates so the move from Design Approaches to MFA or RFA is a change of inputs, not a rewrite.
Common pitfalls in a foundation calculation package
- Mixing approaches. Applying factors to both soil properties and resistances without the code asking for it.
- Unstated ground model. A bearing check with no borehole references or groundwater level.
- Settlement left until last. Serviceability often governs on clay, so check it early.
- No link to construction. Items to be verified on site belong in the report, not in an email afterwards.
- Drawings out of step with calculations. Footing sizes, levels and reinforcement should match the calc revision.
Perspective
We see the same pattern in many UK consultancies: the geotechnical thinking is sound, but the calculation package, the drawings and the report fall out of step when the team is stretched. The fix is rarely a new method. It is capacity that works inside your process, to your templates, to UK standards and Eurocodes.
That is why we embed engineers in a client’s workflow rather than replace it. You keep the client relationship, and we handle calculations, drawings and BIM coordination so outputs reach you review-ready. With the second generation of Eurocode 7 coming, having a team that can run both sets of checks in parallel without a permanent hire is a practical advantage.
Mohammed
Getting extra capacity on foundation work
When foundation packages stack up, the bottleneck is usually engineer hours, not method. We provide remote civil and structural engineers who work inside your workflow on calculations, technical drawings, CAD and BIM modelling, reinforced concrete, steel, timber and foundation design, structural reports and temporary works design, aligned to UK standards and Eurocodes. Projects can kick off within 48 hours, with NDA and non-compete protection, and you stay in direct control of your client.

See how remote engineering support works, or look at our structural engineering services for reports and design packages. If drainage is part of the scheme, our civil engineering team covers surface water and foul drainage design.
FAQ
Is Eurocode 7 mandatory for foundation design in the UK?
Eurocode 7 with its UK National Annex is the standard basis for geotechnical design of buildings and civil engineering works in the UK, and Building Regulations guidance points to it. Check the requirements on your project, including what the contract and the approving body specify. For the current status of British Standards, consult the BSI.
Which parts of Eurocode 7 do I need?
For current work you need BS EN 1997-1:2004 and the UK National Annex, with EN 1997-2:2007 for ground investigation and testing. The second generation has three parts (general rules, ground properties and geotechnical structures), which UK practice will adopt before the first-generation withdrawal on 30 March 2028.
What is the difference between the Material Factor and Resistance Factor Approaches?
The Material Factor Approach applies partial factors to the ground properties, while the Resistance Factor Approach applies them to the calculated resistances. Both are used to show that design effects do not exceed design resistance. Which applies depends on the check and the National Annex.
What should a foundation design report include?
It should cover the site, ground conditions, proposed construction and actions, design values of soil properties with justification, standards applied, calculations and drawings, recommendations, and items to check during construction. It also needs a supervision and monitoring plan.
Sources
- Eurocode 7: Geotechnical design, European Commission Eurocodes portal
- BS EN 1997-1:2024 preview
- BS EN 1997-2:2024, NBS publication index
- JRC: Determination of representative values
- JRC: Assembling the ground model
- ISSMGE: Eurocode 7 second generation, spread foundations
- ISSMGE: 2nd Generation of Eurocode 7
- BS EN 1997-1:2004 Geotechnical design
- ETC10 design examples
- Geocentrix RePUTE tutorial 3
- Geocentrix lecture: Preparing for the 2nd generation Eurocodes