An attenuation tank is sized by finding the largest gap between the water flowing in and the water the flow control lets out, across a range of storm durations. You need the impermeable catchment area, the permitted discharge rate and design rainfall for the 1% annual exceedance probability (AEP) event with a climate-change allowance. The storage volume is the biggest result you get across all durations. The rest of this guide shows how to get each input, run the calculation and avoid the mistakes that leave a tank too small, too big or structurally wrong.
The same logic applies whether your team says attenuation tank, detention tank or storage tank. It is written for UK consultancies, architects and contractors who need a defensible volume for a drainage strategy.
TL;DR
- Tank volume equals the peak of (inflow minus permitted outflow) over the critical storm duration, not the volume of a single arbitrary storm.
- Inputs: impermeable area, permitted discharge rate, 1% AEP rainfall with the current climate-change allowance, and an urban-creep allowance where it applies.
- In England the national SuDS standards expect control of the 1% AEP event, using current climate-change guidance and a 10% urban-creep uplift in most cases.
- Volume is only half the job: exceedance routes, silt treatment, access, groundwater and structural loads decide whether the tank works.
- Quick-method figures are for feasibility. Final sizing needs drainage modelling checked against the lead local flood authority (LLFA) or sewer undertaker’s requirements.
Table of Contents
- What an attenuation tank does, and when it is not the answer
- The inputs you need before you calculate
- How to calculate the storage volume
- Worked example
- Flow control, treatment and sediment
- Exceedance, blockage and the 1% AEP check
- Why a tank ends up undersized, oversized or unsafe
- What the planning submission needs
- Perspective: sizing is the easy part
- Need drainage capacity for your next scheme?
- FAQ
- Sources
What an attenuation tank does, and when it is not the answer
An attenuation tank is an underground store. It collects runoff from roofs and paving, holds it and releases it through a flow control at a limited rate to a sewer or watercourse. The flow control is usually an orifice or a vortex device sitting in a control chamber at the outlet.
A soakaway behaves differently. It stores water temporarily, then lets it infiltrate into the surrounding ground, so it relies on the soil accepting that water. The modular crate technology can be similar for both, but the final route of the water is the essential distinction: a controlled discharge for an attenuation tank, infiltration for a soakaway.
That choice is set by the runoff destination hierarchy in the national SuDS standards for England, which puts infiltration and surface water use ahead of discharge to a watercourse, surface water sewer or combined sewer. Attenuation is what you design when infiltration is not viable, for example on clay, with high groundwater or on contaminated land. If infiltration is possible, start with our guide to soakaway design with percolation tests and BRE 365 calculations, because it changes the whole strategy.

The inputs you need before you calculate
Sizing fails most often because of weak inputs, not weak arithmetic. Collect these first.
Impermeable catchment area
Measure every surface that drains to the tank: roofs, roads, driveways, patios and any paved area. The area is in square metres of impermeable surface, so a permeable paving area counts only to the extent that it generates runoff. Runoff coefficients need careful consideration, and a lazy 100% on everything or an optimistic low figure both distort the answer.
Permitted discharge rate
The permitted outflow limits how fast the tank empties, so it is the single biggest driver of volume. On many sites it is set at the pre-development greenfield rate. Greenfield rates such as Qbar or Qmed must be calculated using the Environment Agency flood estimation guidelines to set the maximum discharge from the developed site. Sewer undertakers and LLFAs can also set their own limits, so confirm the figure in writing before you size anything.
A very low permitted rate pushes the flow control orifice small, which raises blockage risk. That is a design reason to put treatment upstream of the control chamber, covered below.
Design rainfall and return period
The standard design event is 1% AEP, often called the 1 in 100 year storm. The national standards also refer to the 3.3% AEP event, the 1 in 30 year storm, when you check that the system behaves properly in smaller events. Rainfall depth and intensity for your location come from the FEH rainfall datasets, which your modelling software normally holds.
Climate-change allowance
Designs should use the latest climate-change guidance for the 3.3% and 1% AEP events. The government’s guidance on flood risk assessments and climate change allowances gives peak rainfall allowances by management catchment in England, for 1% and 3.3% AEP events. Its 2022 update says the central allowance applies to developments with a lifetime up to 2100 and the upper end allowance to those running from 2100 to 2125. Check the current page for your catchment and development lifetime rather than carrying a percentage over from a previous job. Scotland, Wales and Northern Ireland have their own guidance.
Urban creep
The national standards expect a 10% urban-creep uplift on the impermeable area, except where there are no external private permeable spaces, when the uplift is 0%. Flats with no private gardens are the usual 0% case. Houses with gardens will normally take the 10%.
Site constraints
Groundwater level, drainage invert levels, layout and cover depth do not change the hydraulic volume but they decide whether the volume fits. Groundwater and invert levels in particular determine how deep the tank can sit and whether it needs buoyancy checks.
How to calculate the storage volume
The method below is the standard simplified approach that sits behind most quick-sizing tools. Use it for feasibility, and use a full hydrological model for the submission.
- Work out the design impermeable area. Take the measured area, apply the runoff coefficient and add the urban-creep uplift where it applies.
- Fix the permitted outflow in l/s from the greenfield calculation or the sewer undertaker’s limit.
- Take rainfall depths for the 1% AEP event at a range of durations, from 15 minutes up to 24 hours or more, and apply the climate-change allowance to each.
- For each duration, calculate inflow volume (area multiplied by rainfall depth) and outflow volume (discharge rate multiplied by duration).
- Subtract outflow from inflow. The result is the storage needed for that duration.
- Choose the largest value. That duration is the critical one, and its storage is your design volume.
The critical duration matters because different storm lengths govern different SuDS components. A short intense burst fills a small store quickly, but a long storm with a low outflow rate can need more. With a tight discharge limit, the critical duration is often several hours.
Worked example
The numbers below are illustrative only. The rainfall depths are placeholder values chosen to show the method, not data for any real location, so do not reuse them.
Assume a small commercial yard:
- Impermeable area of 2,000 m², already including any runoff coefficient and urban-creep adjustment
- Permitted discharge of 5 l/s
- Assumed 1% AEP rainfall depths with climate change already applied
| Duration | Assumed rainfall depth | Inflow volume | Outflow at 5 l/s | Storage needed |
|---|---|---|---|---|
| 30 minutes | 33 mm | 66 m³ | 9 m³ | 57 m³ |
| 60 minutes | 45 mm | 90 m³ | 18 m³ | 72 m³ |
| 120 minutes | 58 mm | 116 m³ | 36 m³ | 80 m³ |
| 240 minutes | 72 mm | 144 m³ | 72 m³ | 72 m³ |
| 360 minutes | 82 mm | 164 m³ | 108 m³ | 56 m³ |
The 120-minute storm gives the largest figure, so the critical duration is two hours and the hydraulic storage is about 80 m³. A shorter storm would have under-sized the tank and a longer one would have over-sized it, which is why testing a single event is not enough.
Now see what the discharge limit does. Halve the permitted rate to 2.5 l/s and the outflow figures halve, so the 240-minute row becomes 144 minus 36, or 108 m³, and the critical duration moves later. Discharge rate and critical duration cannot be separated.
The 80 m³ is net storage. A geocellular or crate tank has a void ratio, so the excavation is larger than the water volume. Take the void ratio from the manufacturer’s data for the product you specify, and add the volume of any pipework, control chamber and storage in the upstream network only when your model shows it is usable.

Flow control, treatment and sediment
A tank is a system with a hydraulic control at the end of it. CIRIA guidance expects a flow-control structure, upstream sediment treatment, practical inspection access and an emergency or bypass route for flows above the design event.
On sediment, adding about 10% volume to tanks at risk of silting up is common. CIRIA describes that figure as arbitrary and potentially too large, and prefers sediment forebays and effective upstream treatment to relying only on extra volume. In practice that means a silt trap, catchpit or separator ahead of the tank, sized and maintained properly, rather than a larger tank that silts up more slowly.
Exceedance, blockage and the 1% AEP check
Nominal storage is not the end of the design. The SuDS Manual guidance, as summarised in the research we used, requires an exceedance plan showing that water is contained on site during 1% AEP plus climate-change events without flooding critical infrastructure. It also calls for a maintenance manual covering inspection schedules, cleaning of silt traps and long-term management responsibility.
Exceedance and blockage design is as important as the nominal storage volume. Ask what happens when the orifice blocks, when the tank is already full from a previous storm, or when a storm exceeds the design event. Draw the overland route on the drainage layout and set finished floor levels so the flow runs away from buildings.
Why a tank ends up undersized, oversized or unsafe
These are the problems we see most often when reviewing sizing calculations.
- Wrong or missing urban-creep allowance. Applying 0% where the national standards expect 10% undersizes the tank.
- Out-of-date climate-change figures. Allowances are published by catchment and updated, so copying a percentage from an old report is risky.
- Testing one storm duration. As the worked example shows, the critical duration moves with the discharge rate.
- Over-generous sediment allowance. Extra volume treats the symptom, while upstream treatment treats the cause.
- Ignoring structure. A tank can be hydraulically correct and still be structurally or operationally inadequate. CIRIA’s modular geocellular guidance names inadequate design, overloading, groundwater or construction water, and testing that overestimates strength as principal failure factors. Traffic loads, construction plant, backfill quality, creep and groundwater all belong in the design brief.
- No inspection before backfill. Completed systems should be inspected by a competent person for structural integrity before backfilling and commissioning.
What the planning submission needs
A sizing calculation on its own rarely satisfies a planning officer. The LLFA will usually want to see the volume, the discharge rate and its basis, the climate-change and urban-creep assumptions, the exceedance route, and the maintenance and adoption arrangements. Most LLFAs require attenuation as a condition of drainage approval, and the flow control typically limits discharge to the pre-development greenfield rate. Our article on the drainage strategy report structure that supports UK planning approval walks through how to present these items.
Perspective: sizing is the easy part
We find that the arithmetic of attenuation sizing is rarely where schemes go wrong. The weak points are the inputs agreed late, the discharge limit confirmed verbally and the exceedance route drawn after the layout is frozen.
Our approach is to embed our engineers in your workflow, so the drainage calculation, the layout drawings and the structural checks for the tank are developed together and aligned to UK standards and Eurocodes. When a discharge rate changes after consultation, the volume, the tank footprint and the cover checks change in the same revision, not three weeks later.
For consultancies with a spike in drainage work, that means review-ready calculation packages without a permanent hire, and you keep the client relationship throughout. We can start within 48 hours, and we work under NDA.
Mohammed
Need drainage capacity for your next scheme?
If your team has a surface water strategy to size and not enough hours to do it, our civil engineering service covers surface water and foul drainage design, and we deliver it as calculations and drawings your own team can review and issue.

We also provide dedicated overflow capacity through remote engineering support, with engineers who work inside your processes and your naming conventions. Tell us the site, the discharge constraint and your deadline, and we will scope it from there.
FAQ
What is the difference between an attenuation tank and a detention tank?
In UK practice the two terms are used interchangeably for an underground store that holds runoff and releases it at a controlled rate. The sizing method is the same. Neither relies on infiltration, which is what separates both from a soakaway.
What information do I need to size an attenuation tank?
You need the impermeable catchment area, the permitted discharge rate, and design rainfall for the 1% AEP event with the current climate-change allowance. Add the urban-creep uplift where it applies. Groundwater level and drainage invert levels then decide whether the tank fits on site.
Which storm should I design the tank for?
In England the national SuDS standards expect control of the 1% AEP event, with current climate-change allowances, and the 3.3% AEP event is also referred to. Test a range of durations and take the critical one. Check your LLFA or sewer undertaker for any local variation.
Should I add extra volume for silt?
A 10% addition is common, but CIRIA calls it arbitrary and possibly too large. Better practice is upstream treatment and a sediment forebay where appropriate, with a clear inspection and cleaning regime in the maintenance manual.
Can I use a quick-sizing method for a planning application?
Simplified methods are good for feasibility and early layout decisions. For a submission, your volume should come from a drainage model that uses site-specific rainfall and the agreed discharge rate, and it should include the exceedance plan.
Sources
- National standards for sustainable drainage systems (SuDS), GOV.UK
- Flood risk assessments: climate change allowances, GOV.UK
- Assessing attenuation storage volumes, Susdrain fact sheet
- CIRIA C753 The SuDS Manual, interception design extract
- CIRIA C753 The SuDS Manual
- Structural design of modular geocellular drainage tanks, CIRIA
- Difference between soakaway and attenuation tank (UK)


Leave a Reply