Falsework is the temporary structure that holds up permanent work, and the formwork that shapes it, until the permanent work can carry itself. Designing it well comes down to five things: a written brief, every load the structure will see, lateral stability, a design checked by a competent engineer, and a controlled process for loading and striking. This guide covers each in the order a designer meets them on a UK job.
TL;DR
- Falsework supports the permanent structure and its formwork until the concrete or structure is self-supporting. Formwork gives the shape; falsework holds it up.
- In the UK, the design sits under BS 5975 and BS EN 12812, with the HSE expecting temporary structures to withstand all foreseeable loads.
- Start with a written brief, then check vertical, horizontal and environmental loads, with particular care over lateral stability and foundations.
- Drawings and calculations must be clear enough to build from and for an independent check, with a permit-to-load before use and a permit-to-strike before removal.
- Overflow design capacity can come from an embedded remote engineer rather than a permanent hire.
Table of Contents
- Falsework and formwork: what each one does
- Which UK standards and rules apply
- Step 1: Start with a written brief
- Step 2: Establish the loads
- Step 3: Design for stability, bracing and foundations
- Step 4: Produce drawings and calculations that can be built and checked
- Step 5: Control erection, loading and striking
- Common mistakes at design stage
- Our perspective
- Getting design capacity when you need it
- FAQ
- Sources
Falsework and formwork: what each one does
The two terms get used loosely, and the confusion is understandable because they work as a pair. Formwork is the mould that gives fresh concrete its shape: the faces, soffits and sides. Falsework is the supporting framework underneath and around it: the props, towers, beams, bracing and the ground or foundations they bear on. The Concrete Society describes falsework as needing to carry all vertical, horizontal and inclined loads imposed by the structure it supports, including construction operations and wind.

In practice the split matters because the failure modes differ. Formwork tends to fail locally, through a burst face or a deflecting soffit. Falsework fails globally: a tower buckles, a prop punches into soft ground, or a whole bay sways sideways. That is why falsework design deserves its own calculation and its own checking route, even on a modest job.
Which UK standards and rules apply
Three layers apply: the law, the code of practice and the performance standard.
The law. The HSE states that any temporary structure must be designed, installed and maintained to withstand any foreseeable loads and used only for the purposes for which it was designed. Under CDM 2015, designers and contractors both hold duties for temporary works. We cover this in our guide to CDM 2015 designer duties.
BS 5975. This is the code of practice for temporary works procedures and the permissible stress design of falsework. The 2019 edition was updated to reflect CDM 2015, particularly the interface between permanent works design and temporary works design. BSI published BS 5975-2:2024 on 31 December 2024. It gives recommendations on the design, specification, construction, use and dismantling of falsework, covering permissible stress and limit state design, proprietary equipment and traditional scaffold solutions, and wind loading.
BS EN 12812. This sets performance requirements for falsework in three classes: A, B1 and B2. According to the Concrete Centre, limit state design methods are specified for classes B1 and B2, but the standard gives no structural design guidance for class A. BSI states that BS 5975-2:2024 applies to the design of class A falsework, which BS EN 12812 excludes, and that wind loads are the unfactored loads conforming to both BS EN 1991-1-4 and BS EN 12812.
So the working rule is simple. Identify the class, then use the document that governs that class. Eurocode literacy matters here because the wind and structural steel, concrete and timber checks all lean on permanent works standards.
Step 1: Start with a written brief
The Bragg Report, the 1975 report of the Advisory Committee on Falsework, is old but its first principle still holds: all falsework must be designed, even if on a small job the design is only a simple sketch. It also recommends that the designer, especially one who is not on site, must have a proper written brief covering every factor to be allowed for.
A useful brief includes:
- the permanent structure: geometry, pour sequence, concrete thickness and any prestress or staged loading;
- the required levels, tolerances and finish of the formwork;
- ground information, existing structures, services and bearing capacity;
- site constraints: access, crane reach, adjacent buildings, public protection;
- the intended erection and striking sequence, and the programme;
- the expected construction loads: plant, stacked materials, operatives, concrete placement method.
A brief that arrives as a drawing and a phone call is the commonest source of rework. If you are outsourcing the design, the brief is also what lets a remote engineer start without a week of questions.
Step 2: Establish the loads
BS 5975 groups the loads falsework must cater for into self-weights, imposed loads and environmental loads. In the older 1996 edition, which set out this grouping, the aim was to establish precise loading conditions wherever possible rather than assume them.
Vertical loads
- Self-weight of the permanent element being supported, usually fresh concrete plus reinforcement, and of the formwork and falsework itself.
- Imposed construction loads: operatives, equipment, stacked materials and the dynamic effect of placing concrete.
Check how the load actually reaches the falsework, not only how much of it there is. Load from a deep beam can sit on a few props while an adjacent thin slab loads many.
Horizontal loads
Horizontal loads come from wind, from the pressure of concrete on the formwork, from out-of-plumb erection and from incidental impact or plant movement. The Bragg Report recommended that falsework be designed for a total horizontal load in any direction equal to the calculated loads plus 1% of the vertical load or 3% of the vertical load, whichever is the greater. Today you apply the notional horizontal force provisions of the current code and standard, but the logic is unchanged: a structure that looks vertical on the drawing will not be vertical on site.
Wind and environment
The 2024 revision of BS 5975 changed the maximum wind force calculation to be based on a likely erection duration of one year (formerly two years) with a ten-year return period, according to BSI Knowledge. It also added information on wind with adjacent tall structures, funnelling effects of terrain and buildings, and susceptibility to vortex shedding. If your programme runs longer than the assumed duration, say so in the brief and design accordingly.
Step 3: Design for stability, bracing and foundations
Most falsework collapses are stability failures, not member failures. The Concrete Society says particular care is needed to make sure falsework has adequate lateral stability.
Work through the load path from the top down:
- Formwork and bearers. Check bending, shear and deflection of the formwork and the members that carry it.
- Primary beams and heads. Check bearing, lateral restraint and the connection to the props or towers.
- Props, towers or frames. Check buckling with realistic effective lengths and the capacity of the proprietary equipment at the extension actually used. Proprietary systems are only valid within the manufacturer’s stated limits.
- Bracing and ties. Provide a continuous path for horizontal load to a stable base. Check that bracing stays effective as the structure is struck in stages.
- Bases and ground. Spread the load with sole plates or foundations sized to ground bearing capacity. Consider settlement, water, and any excavation nearby.
The Bragg Report also recommended that the overall factor of safety for falsework as a whole should not be less than two, with a factor of safety defined in BS 5975:1996 as the ratio of ultimate load to maximum working load. Under the limit state route in the current standards the safety philosophy is expressed through partial factors, so follow the method of the document you are designing to and do not mix the two.
A quick sense check before you submit
- Is there a continuous, stated load path from the pour to the ground?
- Are the assumed ground conditions confirmed, not guessed?
- Does the design still work at each stage of the pour and strike, not only when complete?
- Does anything in the sequence leave a tower unbraced?
Step 4: Produce drawings and calculations that can be built and checked
A design is only as good as what reaches the gang on site. BS 5975:1996 defines an erection drawing as a drawing prepared before erection showing the arrangement and details of the falsework structure. The same code notes that where construction is not straightforward, the drawings are unlikely to set down every detail, so a method statement or construction plan should be prepared and made available to everyone concerned, with instructions on preparing the supporting foundations.
A reviewable package normally contains:
| Item | What it should show |
|---|---|
| Design brief and assumptions | Loads, ground, class of falsework, programme, standards used |
| Calculations | Load take-down, member and connection checks, stability, ground bearing |
| Erection drawings | Plan, sections, member sizes, levels, bracing, bases, tolerances |
| Sequence information | Pour order, striking order, any staged propping or reshoring |
| Interface notes | Loads imposed on the permanent works, with comment from its designer |
The Bragg Report adds that the falsework design and, if requested, the calculations should go to the designer of the permanent works for comment, and that the initial design of any falsework other than minor, and any significant later alteration, must be approved by a fully qualified engineer. If a design contains novel features, the contractor should arrange an independent check.
Clear calculations make that check quick. State each assumption, label each load case and cross-reference every result to a drawing detail. For more on how we handle the wider process, see our piece on temporary works design under BS 5975.
Step 5: Control erection, loading and striking
Design does not end when the drawings are issued. The HSE’s guidance in CIS56 sets out the controls:
- Before erection, carry out a risk assessment and develop a safe system of work. Prepare a method statement covering how the hazards will be managed, and make sure those doing the work have read and understood it.
- Keep falsework stable at every stage of erection and check it regularly.
- When complete, inspect and certify all falsework as ready for use. A written permit-to-load procedure is strongly recommended.
- The temporary works co-ordinator should agree the time of striking for each section, again with a written permit-to-strike procedure strongly recommended.
- During dismantling, workers must be able to work safely without being injured by falling objects.
The temporary works co-ordinator is the person who keeps these steps joined up: the brief, the design check, the permits and the inspection record. Our article on temporary works coordination and permits explains how that role fits with the design team.
Note that CIS56 was written when BS 5975 was the governing code with BS EN 12812 to follow, so cross-check the current editions of both when you specify the standard in your method statement.
Common mistakes at design stage
- Designing only the final condition. Falsework is most vulnerable mid-pour and during striking.
- Assuming the ground. A sole plate on unverified ground is a guess, not a design.
- Ignoring lateral loads. Plumb props on a drawing are not plumb on site.
- Forgetting the permanent works. The falsework can load the permanent structure in ways it was never designed for, which is why the permanent works designer should see the design.
- Out-of-date wind assumptions. Check which edition of the code your design uses and whether the exposure assumptions still match the programme.
- No independent check. Novel arrangements and anything beyond minor work need approval by a suitably qualified engineer.
Our perspective
Most of the falsework problems we see are not exotic. They are a thin brief, a late change in pour sequence, or a design that sits with one overstretched engineer until the day before erection.
UK consultancies and contractors tend to hit this at the same moment: a pour date is fixed, the temporary works queue is long, and a permanent hire is the wrong answer to a peak that will pass. That is the situation our remote model is built for. We embed experienced civil and structural engineers into your workflow to produce calculations, drawings and BIM coordination aligned to UK standards and Eurocodes, leaving you in control of your client relationship.
What makes the difference is discipline at the front end: a written brief, stated assumptions, load cases that match the construction sequence and a package that is review-ready for your own checker. We agree NDA terms up front and can kick off quickly, so the design is not the thing holding up the programme.
Mohammed
Getting design capacity when you need it
If your team is stretched on temporary works calculations, erection drawings or the structural reports that sit around them, we can embed a remote engineer into your process rather than adding permanent headcount. Our remote engineering support covers calculations, drawings and BIM coordination for UK consultancies, and our temporary works design service sits within that offer. Projects start with a brief, so the checklist above is a good place to begin.

We aim to get projects started within 48 hours, with NDA and non-compete protection in place. You can see how this works in practice in our case study on scaling a small structural consulting firm, or look at our structural engineering work for the permanent-works side.
FAQ
Do small falsework jobs need a design?
Yes. The Bragg Report recommends that all falsework is designed, even if on a small job the design is only a simple sketch. What changes with scale is the depth of the calculation and the level of checking, not whether a design exists.
Which standard should I use for falsework design in the UK?
BS 5975 is the UK code of practice for temporary works procedures and falsework design, and BS EN 12812 sets performance requirements for falsework. BS 5975-2:2024 applies to class A falsework, which BS EN 12812 excludes from its design rules. Confirm the class first, then follow the matching document.
What is a permit-to-load and a permit-to-strike?
They are written sign-offs that control when falsework can take load and when it can be removed. The HSE’s CIS56 says completed falsework should be inspected and certified as ready for use, and strongly recommends written permit-to-load and permit-to-strike procedures. The temporary works co-ordinator agrees the striking time for each section.
Who should approve a falsework design?
The Bragg Report recommends that the initial design of any falsework other than minor, and any significant later alteration, is approved by a fully qualified engineer. Where a design has novel features, the contractor should arrange for an independent assessor to check it. The designer of the permanent works should also be able to comment.
Can falsework design be outsourced?
Yes, provided the brief is clear and the output goes through your own checking and permit process. A remote engineer can prepare calculations and drawings to UK standards while your team keeps the client relationship and sign-off.
Sources
- BS 5975-2:2024, BSI Knowledge
- BS 5975:2019, BSI Knowledge
- Final report of the Advisory Committee on Falsework (Bragg Report)
- Design of falsework, Concrete Society
- Temporary works, HSE
- CIS56: Safe erection, use and dismantling of falsework, HSE
- Standards for workmanship and temporary works, Concrete Centre
- BS 5975:1996 Code of practice for falsework